UPCOMING WORK
CBG Building Company reached a significant milestone as we topped out the structure in September 2025, while the bridge construction continues through October 2025. The facade will continue through the end of 2025.
Dominion Energy (DEV) has commenced with managing their work associated with permanent power along N Lynn and 19th Street, which is expected to continue through the January 2026.
Hover or click on a calendar item for details regarding any work activities that will have specific or atypical community impacts (i.e. road closures, night work, etc.). If no items are indicated, no specific community impacts are anticipated at this time.
LATEST PROGRESS
September 2025
The building structure has topped out and the bridge has commenced connecting the two towers on the 26th floor. The exterior facade continues for the brick and Quest towers.