North Crane Dismantle

Road closures for tower crane dismantle will begin at 8 am on 10/17 and continue through 10/19.

View Event →
Aug
12

Morning Bridge Steel Delivery

These deliveries will be on the East side of the project along N Lynn Street with an associated night work permit due to the size of the deliveries and to minimize the impacts to traffic as we offload the eight 12,000 Lb beams.

View Event →
Aug
11

Morning Bridge Steel Delivery

These deliveries will be on the East side of the project along N Lynn Street with an associated night work permit due to the size of the deliveries and to minimize the impacts to traffic as we offload the eight 12,000 Lb beams.

View Event →
Jun
11

Tower Crane Erection

The South Tower crane will be erected along N Moore Street near 19th Street. The crane used for the erection shall be stationed inside of the excavation.

View Event →
Mar
27

Begin RCA Building Demolition - North Garage

The first phase of demolition will begin at the north garage area. We anticipate this will take about two weeks to complete. Once the north garage is demolished, we will begin knocking down the pedestrian sky bridge over N. Moore St. All demolition associated with the bridge will only take place on weekends due to the closure of N. Moore St.