UPCOMING WORK

CBG Building Company continues with completing the facade and hardscape in preparation for Core & Shell in 2026.

Dry utility work (power) continues along N Lynn and 19th Street, which is expected to continue through Q2 2026.

Hover or click on a calendar item for details regarding any work activities that will have specific or atypical community impacts (i.e. road closures, night work, etc.). If no items are indicated, no specific community impacts are anticipated at this time.


LATEST PROGRESS

February 2026

The exterior facade nears completion, while the hardscape commences.